N.Y. Lien Law Section 4-A
Insurance proceeds liable for demands


Owner, contractor or subcontractor diverting proceeds, guilty of larceny. The proceeds of any insurance which by the terms of the policy are payable to the owner of real property improved, and actually received or to be received by him because of the destruction or removal by fire or other casualty of an improvement on which lienors have performed labor or services or for which they have furnished materials, shall after the owner has been reimbursed therefrom for premiums paid by him, if any, for such insurance, be subject to liens provided by this act to the same extent and in the same order of priority as the real property would have been had such improvement not been so destroyed or removed. The proceeds of any insurance which by the terms of the policy are payable to a contractor or subcontractor, and actually received or to be received by him because of the destruction or removal by fire or other casualty of an improvement on which he has performed labor or services or for which he has furnished materials, shall, after such contractor or subcontractor has been reimbursed therefrom for premiums paid by him, if any, for such insurance, be liable for the payment of demands for labor or services performed or materials furnished by his order and for which he is liable, in the same manner and under the same conditions as payments to him under his contract would have been had such improvement not been so destroyed or removed.

Source: Section 4-A — Insurance proceeds liable for demands, https://www.­nysenate.­gov/legislation/laws/LIE/4-A (updated Sep. 22, 2014; accessed Oct. 26, 2024).

3
Mechanic’s lien on real property
4
Extent of lien
4‑A
Insurance proceeds liable for demands
5
Liens under contracts for public improvements
6
Liens for labor on railroads
7
Liability for advance payments, collusive mortgages and incumbrances
8
Terms of contract may be demanded
9
Contents of notice of lien
10
Filing of notice of lien
11
Service of copy of notice of lien
11‑A
Notice of completion and acceptance may be demanded
11‑B
Copy of notice of lien to a contractor or subcontractor
11‑C
Copy of notice of lien to a contractor or subcontractor with respect to public improvements liens
12
Notice of lien on account of public improvements
12‑A
Amendment
13
Priority of liens
14
Assignment of lien
15
Assignments of contracts and orders to be filed
16
Assignment of contracts and orders for public improvement to be filed
17
Duration of lien
18
Duration of lien under contract for a public improvement
19
Discharge of lien for private improvement
20
Discharge of lien after notice of lien filed by payment of money into court
21
Discharge of lien for public improvement
21‑A
Vacating lien for a public improvement, by order of court
22
Building loan contract
23
Construction of article
24
Enforcement of mechanic’s lien
25
Priority of liens and assignments under contracts for public improvements
26
Subordination of liens after agreement with owner
28
Lien of certain judgments postponed
29
Subordination of liens to subsequent mortgage
30
Subordination of notices of lis pendens
31
Discharge of liens on sale of real property
32
Certain liens and claims not to be affected
33
Certain sections not to apply to laborers’ liens
34
Waiver of lien
35
Waiver of arbitration
37
Bond to discharge all liens
38
Itemized statement may be required of lienor
39
Lien wilfully exaggerated is void
39‑A
Liability of lienor where lien has been declared void on account of wilful exaggeration
39‑C
Repossession of materials not used

Accessed:
Oct. 26, 2024

Last modified:
Sep. 22, 2014

§ 4-A’s source at nysenate​.gov

Link Style