N.Y. Lien Law Section 11-B
Copy of notice of lien to a contractor or subcontractor


Within five days before or thirty days after filing a notice of lien in accordance with § 10 (Filing of notice of lien)section ten of this chapter or the filing of an amendment of notice of lien in accordance with § 12-A (Amendment)section twelve-a of this chapter the lienor shall serve a copy of such notice or amendment by certified mail on the contractor, subcontractor, assignee or legal representative for whom he was employed or to whom he furnished materials or if the lienor is a contractor or subcontractor to the person, firm or corporation with whom the contract was made. A lienor having a direct contractual relationship with a subcontractor or a sub-subcontractor but not with a contractor shall also serve a copy of such notice or amendment by certified mail to the contractor. Failure to file proof of such a service with the county clerk within thirty-five days after the notice of lien is filed shall terminate the notice as a lien. Any lienor, or a person acting on behalf of a lienor, who fails to serve a copy of the notice of lien as required by this section shall be liable for reasonable attorney’s fees, costs and expenses, as determined by the court, incurred in obtaining such copy.

Source: Section 11-B — Copy of notice of lien to a contractor or subcontractor, https://www.­nysenate.­gov/legislation/laws/LIE/11-B (updated Feb. 20, 2015; accessed Apr. 13, 2024).

3
Mechanic’s lien on real property
4
Extent of lien
4–A
Insurance proceeds liable for demands
5
Liens under contracts for public improvements
6
Liens for labor on railroads
7
Liability for advance payments, collusive mortgages and incumbrances
8
Terms of contract may be demanded
9
Contents of notice of lien
10
Filing of notice of lien
11
Service of copy of notice of lien
11–A
Notice of completion and acceptance may be demanded
11–B
Copy of notice of lien to a contractor or subcontractor
11–C
Copy of notice of lien to a contractor or subcontractor with respect to public improvements liens
12
Notice of lien on account of public improvements
12–A
Amendment
13
Priority of liens
14
Assignment of lien
15
Assignments of contracts and orders to be filed
16
Assignment of contracts and orders for public improvement to be filed
17
Duration of lien
18
Duration of lien under contract for a public improvement
19
Discharge of lien for private improvement
20
Discharge of lien after notice of lien filed by payment of money into court
21
Discharge of lien for public improvement
21–A
Vacating lien for a public improvement, by order of court
22
Building loan contract
23
Construction of article
24
Enforcement of mechanic’s lien
25
Priority of liens and assignments under contracts for public improvements
26
Subordination of liens after agreement with owner
28
Lien of certain judgments postponed
29
Subordination of liens to subsequent mortgage
30
Subordination of notices of lis pendens
31
Discharge of liens on sale of real property
32
Certain liens and claims not to be affected
33
Certain sections not to apply to laborers’ liens
34
Waiver of lien
35
Waiver of arbitration
37
Bond to discharge all liens
38
Itemized statement may be required of lienor
39
Lien wilfully exaggerated is void
39–A
Liability of lienor where lien has been declared void on account of wilful exaggeration
39–C
Repossession of materials not used

Accessed:
Apr. 13, 2024

Last modified:
Feb. 20, 2015

§ 11-B’s source at nysenate​.gov

Link Style